[单选题]The process of()schedule activity durations uses information on schedule activityscope of work, required resource types, estimated resource quantities, and resource calendarswith resource availabilities.
A. estimating
B. defining
C. planning
D. sequencing
查看答案&解析
查看所有试题
学习资料:
[单选题]()is the budgeted amount for the work actually completed on the schedule activity or WBS component during a giving time period.
A. Plannedvalue
B. Earned value
C. Actualcost
D. Costvariance
[单选题]The parties to government procurement refer to the principal entities of all kinds that enjoy rights and undertake obligations in government procurement, including the procuring entities, the ()and the procuring agencies.
A. users
B. servers
C. producers
D. suppliers
[单选题]Estimating schedule activity costs involves developing an (1) of the cost of theresources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. for example, in most application areas, additionalwork during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations. the cost estimating process considers whether the expected savings can offset the cost of the additional design work. cost estimates are generally expressed in units of (2) to facilitate comparisons both within and across projects.the (3) describes important information about project requirement that is considered during cost estimating.
A. D