正确答案: C
performingorganization
题目:Project Quality Management processes include all the activities of the()that determine quality policies, objectives and responsibilities so that the project will satisfy theneeds for which it was undertaken.
解析:该题的关键词为"determine quality policies,objectives and responsibilities",其语句结构为"Project Quality Management processes(主语)include(谓语)all the activities of the (宾语)that determine quality policies,objectives and responsibilities(定语从句)",含义为"项目质量管理过程包括决定质量政策、质量目标以及质量责任的什么的所有活动",根据项目质量管理知识,只有组织才可以决定项目的质量政策,因而此处选择选项C。
查看原题 查看所有试题
学习资料的答案和解析:
[单选题]The()technique involves using project characteristics in a mathematical model to predict total project cost. Models can be simple or complex.
costaggregation
解析:可以注意到该题的关键词为"mathematical model"和"predict total project cost",再划分语句结构"The()technique(主语)involves(谓语)using project characteristics in a mathematical model to predict total project cost",易理解语句含义为"什么技术使用数学模型预测项目的总成本"。观察四个选项,ABD也可能应用数学模型,也可能只是简单的数字规定,但选项C 一定会应用数学模型,所以应该选择parametric estimating。
[单选题]()is a category assigned to products or services having the samefunctional use but different technical characteristics. Itisnotsameasquality.
Grade
解析:该题的关键词为"same functional use、 different technical characteristics",其主要语句结构为" ()is a category",含义为"什么是类别",后续的定语从句说明category都有什么特点,即功能相同而技术特征不同,而这正是等级( Grade)的定义。所以选择选项B。
[单选题]The()process analyzes the effect of risk events and assigns a numerical rating to those risks.
Quantitative RiskAnalysis
解析:该题的关键词为"analyzes the effect of risk, numerical rating",其语句结构为"The()一process(主语)analyzes(谓语)the effect of risk events(宾语)and assigns(并列谓语)anumerical rating to those risks(并列宾语)",含义为"什么过程分析风险事件的后果,并且为这些风险指定数值级别",容易判断题目描述的是量化风险分析的特点,应该选择选项B。
[单选题]Project work packages are typically decomposed into smaller components called activities to provide a basis for()scheduling, executing, and monitoring and controllingthe proj ect work.
estimating
解析:该题的关键词为"scheduling、executing、monitoring、controlling",其语句结构为''Project work packages(主语)are typically decomposed into(谓语)smaller components",含义为"项目工作包通常被分解为更小的活动",分析后得知空白处的选项应该和上述的关键词为并列的词语,且顺序排列在其他的关键词之前,因而只能选择选项B,因为只有首先进行项目估算,才能制定项目进度,然后才能执行和监控,其他选项不符合题意。
[单选题]Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the level()
workpackage
[单选题]In which form of projects origination would the project manager be likely to exercise the most control over Project resources.()
Projectized
[单选题](1) is a method of constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activities and connects them with arrows that show the dependencies.This method includes following types of dependencies or precedence relationships: (2) the initiation of the successor activity, depends upon the completion ofthe predecessor activity.(3) the initiation ofthe successor activity, depends upon the initiation ofthe predecessor activity.