[单选题]A ()is a collection of projects and other work that are grouped together to facilitate effective management ofthat work to meet strategic business objectives.
A. program
B. portfolio
C. projectoflargesize
D. PMO
查看答案&解析
查看所有试题
学习资料:
[单选题]() is a measurable, verifiable work product such as specification. feasibility study report, detail document, or working prototype
A. milestone
B. deliverable
C. etc
D. BAC
[单选题]() are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion; they may also exert influence over the project and its results.
A. controls
B. baselines
C. projectstakeholders
D. projectmanagers
[单选题]The()defines the phases that connect the beginning of a project to its end.
A. schedule
B. project life cycle
C. temporary
D. milestone
[单选题]The()Process Group consists of the processes used to complete the work defined in the project management plan to accomplish the project's requirements.
A. Planning
B. Executing
C. Monitoring and Controlling
D. Closing
[单选题]Define Activities is the process ofidentifying the specific actions to be performed toproduce the()
A. projectelements
B. work drafts
C. workpackage
D. projectdeliverables
[单选题]Your project is behind schedule due to conflict between team members . Havingresolved the conflict, to get the project back on schedule , you should consider ().
A. crashing the schedule
B. performing resource leveling
C. conducting reverse resource allocation scheduling
D. utilizing the critical chain resources
[单选题]Estimating schedule activity costs involves developing an (1) of the cost of theresources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. for example, in most application areas, additionalwork during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations. the cost estimating process considers whether the expected savings can offset the cost of the additional design work. cost estimates are generally expressed in units of (2) to facilitate comparisons both within and across projects.the (3) describes important information about project requirement that is considered during cost estimating.
A. A