[单选题]In the project management context()includes characteristics of unification,consolidation, articulation, and integrative actions that are crucial to project completion,successfully meeting customer and other stakeholder requirements, and managing expectations.
A. integration
B. scope
C. process
D. charter
查看答案&解析
查看所有试题
学习资料:
[单选题]You are working on the cost budget for one project. Which of the following is true()
A. This process assigns cost estimates to project activities including risks and contingency plans.
B. The cost baseline will be used to measure variances and future project performance.
C. This process assigns cost estimates for expected future period operating costs.
D. The cost baseline is the expected cost for the project.
[单选题]Quality planning tools are often used to help plan effective quality management activities . ()is one of such tools, which involves company actual or planned project practices to those or other projects to generate ideas for improvement and to provide a basis by which to measure performance.
A. Benchmarking
B. Quality metric
C. Quality checklist
D. Brainstornung