正确答案: D
suppliers
题目:The parties to government procurement refer to the principal entities of all kinds that enjoy rights and undertake obligations in government procurement, including the procuring entities, the ()and the procuring agencies.
查看原题 查看所有试题
学习资料的答案和解析:
[单选题]() from one phase are usually reviewed for completeness and accuracy and approved before work starts on the next phase.
Deliverables
解析:该题的关键词为"from one phase. reviewed. the next phase",其语句结构为" ()fromone phase(主语)are usually reviewed(谓语)for completeness and accuracy and approved before work starts on the next phase",含义为"在开始下阶段之前,需要评审前阶段什么的完整性和准确性",结合选项分析,容易排除A和B,选项C过于笼统,因而选择选项D。
[单选题]Project work packages are typically decomposed into smaller components called activities to provide a basis for()scheduling, executing, and monitoring and controllingthe proj ect work.
estimating
解析:该题的关键词为"scheduling、executing、monitoring、controlling",其语句结构为''Project work packages(主语)are typically decomposed into(谓语)smaller components",含义为"项目工作包通常被分解为更小的活动",分析后得知空白处的选项应该和上述的关键词为并列的词语,且顺序排列在其他的关键词之前,因而只能选择选项B,因为只有首先进行项目估算,才能制定项目进度,然后才能执行和监控,其他选项不符合题意。
[单选题]The creation ofa work breakdown structure (WBS) is the process of()the major project deliverables.
subdividing
解析:该题的关键词为"work breakdown structure、 major project deliverables",其语句结构为"The creation ofa work breakdown structure (WBS)(主语)is(谓语)the processof()the major project deliverables",含义为"创建WBS是怎样主要的项目交付物的过程"。根据WBS定义以及选项,容易识别出应选择分解(subdividing)
[单选题]Changes may be requested by any stakeholder involved with the project, but changes can be authorized only by()
change control board
[单选题]You are working on the cost budget for one project. Which of the following is true()
The cost baseline will be used to measure variances and future project performance.