正确答案: C
Temporary
题目:()means that every project has a definite beginning and a definite end.
解析:该题的关键词为"a definite beginning and a definite end",其语句结构为" (主语)means(谓语)that",含义为"什么意味着",该题干为项目管理的一个基本概念描述,描述了项目具备临时性特点。所以选择选项C。
查看原题 查看所有试题
学习资料的答案和解析:
[单选题]() is a measurable, verifiable work product such as specification. feasibility study report, detail document, or working prototype
deliverable
解析:该题的关键词为"work product",其语句结构为" ____(主语)is(谓语)a measurable,verifiable work product",含义为"什么是可度量的、可验证的工作产品",排除其他选项后容易选出deliverable(交付物)。
[单选题]The receiving activities conduct analyses of the requirements with the requirements provider to ensure that a compatible, shared understanding is reached on the meaning of the requirements. The result ofthis analysis and dialog is an()set of requirements.
agreed-to
解析:该题的关键词为"compatible, shared understanding",其主要的语句结构为"The result of this analysis and dialog(主语)is(谓语)an____set of requirements(表语)",含义为"分析和讨论对应的结果为一组什么的需求",根据题意,应该是达成一致的需求集,所以从选项中识别短语,判断短语的正确形式,此处应该选择agreed-t0。agree with表示同意某人,agree to表示同意某事,此处的"同意"作为形容词性质出现,所以应该使用agreed to形式,其他都不对。
[单选题]In which form of projects origination would the project manager be likely to exercise the most control over Project resources.()
Projectized
[单选题]Contract closeout is a process that involves()
Product verification and administrative closeout
[单选题]Estimating schedule activity costs involves developing an (1) of the cost of theresources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. for example, in most application areas, additionalwork during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations. the cost estimating process considers whether the expected savings can offset the cost of the additional design work. cost estimates are generally expressed in units of (2) to facilitate comparisons both within and across projects.the (3) describes important information about project requirement that is considered during cost estimating.
解析:阅读试题可知,整段文章讨论的内容集中于"Costestimating",分析问题(1)的语句结构为"estimatingscheduleactivitycosts(主语)involves(谓语)developingan (1) ofthecostoftheresources"。接下来使用排除法,如果对于"estimatingscheduleactivitycosts"的特定内容不了解,似乎哪个选项也可以,注意"thelresourcesneededtocompleteeachscheduleactivity",既然每项活动所需的资源都需考虑,那就只能选择答案summary,summary在此处解释为"汇总"。分析问题(2)对应的语句,"costestimates(主语)aregenerallyexpressed(谓语)inunitsof (2) tofacilitatecomparisonsbothwithinandacrossprojects",结合选项,此句的含义为"成本估算(结果)通常以作为单位",故而只能选择C,Currency的含义为"货币"、"通货",考生即使不熟悉这个单词,也能轻易排除其他三个选项。问题(3)对应的语句,"the (3)(主语)describes(谓语)importantinformationaboutprojectrequirementthatisconsideredduringcostestimating",所以该句的含义即"描述了成本估算时应考虑的项目需求"。显而易见,选项C和D容易排除,但选择"Projectscopestatement"还是"Scopeofwork"?Scopeofwork(工作说明书)是合同中的附件,用于说明合同的工作范围(此时项目尚未建立),因而选择选项A。
[单选题]The (1) is a general description of the architecture of a workflow management system used by the WFMC, in which the main components and the associated interfaces are summarized. The workflow enactment service is the heart of a workflow system which consists of several (2).
解析:(1)题的关键词为"work flow management system",其语句结构为"The()(主语)1S(谓语)agener aldescription(表语)",含义为"什么是通用的描述",结合选项应该选择选项B。(2)题的关键词为"work flow enactment service",其语句结构为"The work flow enactment service(主语)is(谓语)the hear to fa work flow system(表语)whichconsistsofseveral()(定语从句)",含义为"工作流定制服务是工作流系统的核心,它由几个什么组成",结合选项应该选择选项A。(1)题和(2)题考查了工作流相关的基本概念,如果了解工作流相关知识则不难做出选择。对于只有硬件背景的考生,(1)题相对容易,(2)题则只能碰运气了。