[单选题]()means that every project has a definite beginning and a definite end.
正确答案 :C
Temporary
解析:该题的关键词为"a definite beginning and a definite end",其语句结构为" (主语)means(谓语)that",含义为"什么意味着",该题干为项目管理的一个基本概念描述,描述了项目具备临时性特点。所以选择选项C。
[单选题]The()Process Group consists of the processes used to complete the work defined in the project management plan to accomplish the project's requirements.
正确答案 :B
Executing
解析:该题的关键词为"accomplish the project's requirements",其语句结构为"The()Process Group(主语)consists of(谓语)the processes used to complete the work defined",含义为"用于完成工作的过程组成什么过程组",所以可知重点描述为"完成工作",根据项目管理五个过程组的特点,选择Executing(执行)过程组,其他选项容易排除。
[单选题]The()provides the project manager with the authority to apply organizational resources to project activities.
正确答案 :D
projectcharter
解析:该题的关键词为"authority to apply organizational resources",其语句结构为"The____(主语)provides(谓语)the project manager with the authority to apply organizationalresources",含义为"什么为项目经理提供了使用组织资源的权力",根据项目管理知识,为项目经理授权的文件为项目章程,所以应该选择选项D,其他选项容易排除。
[单选题]The()describes, in detail, the project's deliverables and the work required to create those deliverables.
正确答案 :
[单选题]PDM includes four types of dependencies or precedence relationships:().The completion ofthe successor activity depends upon the initiation of the predecessor activity.
正确答案 :D
Start-to-Finish
解析:该题的关键词为"PDM includes four types",其语句结构为"The completion of the successor activity(主语)depends upon(谓语)the initiation of the predecessor activity",含义为"后续活动的完成依赖于前置活动的开始",根据选项容易识别为SF活动依赖类型。
[单选题]()involves using mathematical techniques to forecast future outcomes based onhistorical results.
正确答案 :A
Trendanalysis
解析:该题的关键词为"mathematical techniques、 forecast future outcomes",其语句结构为"____(主语)involves(谓语)using mathematical techniques to forecast future outcomes(宾语从句)",含义为"什么涉及使用数学方法预测未来结果",结合选项分析,虽然都是质量管理方法,但其中只有Trend analysis用于预测未来结果,Quality audit为质量审计,Defect repair review为缺陷补救审查,Flowcharting为流程图,均不涉及对未来结果进行预测。
[单选题]You are working on the cost budget for one project. Which of the following is true()
正确答案 :B
The cost baseline will be used to measure variances and future project performance.
[单选题]A ()is a collection of projects and other work that are grouped together to facilitate effective management ofthat work to meet strategic business objectives.
正确答案 :B
portfolio
[单选题]There are strategies typically deal with threats or risk that may have negative impacts on project objectives if they occur, some other strategies are suggested to deal with risks with potentially positive impacts. ()is a risk response strategy that may be adopted for either threats or opportunities.
正确答案 :D
Acceptance
[单选题](1) is a method of constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activities and connects them with arrows that show the dependencies.This method includes following types of dependencies or precedence relationships: (2) the initiation of the successor activity, depends upon the completion ofthe predecessor activity.(3) the initiation ofthe successor activity, depends upon the initiation ofthe predecessor activity.
正确答案 :
查看原题 查看所有试题