• [单选题]Project()Management includes the processes required to ensure that theproj ect includes all the work required, and only the work required, to complete the project successfully.
  • 正确答案 :B
  • Scope

  • 解析:该题的关键词为"all the work required, only the work required",其语句结构为"Project()Management(主语)includes(谓语)the processes",含义为"项目什么管理包含过程",仅根据关键词便可判断出应该与项目范围管理紧密相关,在结合语句分析,应该选择项目范围管理,即Scope。

  • [单选题]The TCP protocolis a ()layer protocol.
  • 正确答案 :C
  • transport


  • [单选题](1) is a method of constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activities and connects them with arrows that show the dependencies.This method includes following types of dependencies or precedence relationships: (2) the initiation of the successor activity, depends upon the completion ofthe predecessor activity.(3) the initiation ofthe successor activity, depends upon the initiation ofthe predecessor activity.
  • 正确答案 :

  • 查看原题 查看所有试题


    推荐科目: 计算机网络知识题库 面向对象系统分析与设计题库 信息安全知识题库 初级网络管理员题库 项目沟通管理题库 项目人力资源管理题库 文档与配置管理题库 初级程序员题库 业务流程管理和重组题库 高级网络规划设计师题库
    @2019-2025 必典考网 www.51bdks.net 蜀ICP备2021000628号 川公网安备 51012202001360号