The()provides the project manager with the authority to ap

  • 下载次数:
  • 支持语言:
  • 1730
  • 中文简体
  • 文件类型:
  • 支持平台:
  • pdf文档
  • PC/手机
  • 【名词&注释】

    关键词、项目经理(project manager)、项目管理知识

  • [单选题]The()provides the project manager with the authority to apply organizational resources to project activities.

  • A. project management plan
    B. contract
    C. project human resource plan
    D. projectcharter

  • 查看答案&解析 查看所有试题
  • 学习资料:
  • [单选题]PDM includes four types of dependencies or precedence relationships:().The completion ofthe successor activity depends upon the initiation of the predecessor activity.
  • A. Finish-to-Start
    B. Finish-to-Finish
    C. Start-to-Start
    D. Start-to-Finish

  • [单选题]Changes may be requested by any stakeholder involved with the project, but changes can be authorized only by()
  • A. executive IT manager
    B. projectmanger
    C. change control board
    D. projectsponsor