1. [单选题]Organizations perform work to achieve a set of objectives. Generally, work can be categorized as either projects or operations, although the two sometimes are()
A. confused
B. same
C. overlap
D. dissever
2. [单选题]Project Quality Management processes include all the activities of the()that determine quality policies, objectives and responsibilities so that the project will satisfy theneeds for which it was undertaken.
A. Project
B. project management team
C. performingorganization
D. customer
3. [单选题]Project work packages are typically decomposed into smaller components called activities to provide a basis for()scheduling, executing, and monitoring and controllingthe proj ect work.
A. reviewing
B. estimating
C. auditing
D. expecting
4. [单选题]You are working on the cost budget for one project. Which of the following is true()
A. This process assigns cost estimates to project activities including risks and contingency plans.
B. The cost baseline will be used to measure variances and future project performance.
C. This process assigns cost estimates for expected future period operating costs.
D. The cost baseline is the expected cost for the project.
5. [单选题]The (1) is a general description of the architecture of a workflow management system used by the WFMC, in which the main components and the associated interfaces are summarized. The workflow enactment service is the heart of a workflow system which consists of several (2).
A. B