1. [单选题]The()Process Group consists of the processes used to complete the work defined in the project management plan to accomplish the project's requirements.
A. Planning
B. Executing
C. Monitoring and Controlling
D. Closing
2. [单选题]Project Quality Management processes include all the activities of the()that determine quality policies, objectives and responsibilities so that the project will satisfy theneeds for which it was undertaken.
A. Project
B. project management team
C. performingorganization
D. customer
3. [单选题]()is a property of object-oriented software by which an abstract operation may be performed in different ways in different classes.
A. Method
B. Polymorphism
C. Inheritance
D. Encapsulation
4. [单选题]Many useful tools and techniques are used in developing schedule()is a schedule network analysis technique that modifies the project schedule to account for limited resource.
A. PERT
B. Resourceleveling
C. Schedulecompression
D. Critical chain method
5. [单选题]Configuration management system can be used in defining approval levels for authorizing changes and providing a method to validate approved changes.()is not a project configuration management tool.
A. RationalClearcase
B. QualityFunctionDeployment
C. VisualSourceSafe
D. ConcurrentVersions System
6. [单选题]Project selection methods involve measuring value or attractiveness to the project owner or sponsor and may include other organizational decision criteria ()is not a project selection method.
A. Benefitcontribution
B. Expertjudgment
C. Scoringmodels
D. Flowcharting
7. [单选题]In which form of projects origination would the project manager be likely to exercise the most control over Project resources.()
A. Strongmatrix
B. Projectized
C. Projectcoordinator
D. Weakmatrix
8. [单选题]Contract closeout is a process that involves()
A. Customer satisfaction analysis and final payment
B. Administrative closeout and archiving records
C. Finial contractor payment and Lessons learned
D. Product verification and administrative closeout
9. [单选题]A ()is a collection of projects and other work that are grouped together to facilitate effective management ofthat work to meet strategic business objectives.
A. program
B. portfolio
C. projectoflargesize
D. PMO
10. [单选题]Estimating schedule activity costs involves developing an (1) of the cost of theresources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. for example, in most application areas, additionalwork during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations. the cost estimating process considers whether the expected savings can offset the cost of the additional design work. cost estimates are generally expressed in units of (2) to facilitate comparisons both within and across projects.the (3) describes important information about project requirement that is considered during cost estimating.
A. C