必典考网发布高级信息系统项目管理师题库2022专业英语题库免费模拟考试题245,更多专业英语题库的模拟考试请访问必典考网高级信息系统项目管理师题库频道。
1. [单选题]The()technique involves using project characteristics in a mathematical model to predict total project cost. Models can be simple or complex.
A. costaggregation
B. reserve analysis
C. parametricestimating
D. funding limit reconciliation
2. [单选题]Project Quality Management must address the management of the project and the()ofthe project. While Project Quality Management applies to all projects,regardless of the nature of their product, product quality measures and techniques are specific to the particular type of product produced by the project.
A. performance
B. process
C. product
D. object
3. [单选题]The project()is a key input to quality planning since it documents major project deliverables, the project objectives that serve to define important stakeholder requirements,thresholds, and acceptance criteria.
A. work performance information
B. scope statement
C. changerequests
D. process analysis
4. [单选题]Performing()involves monitoring specific project results to determine if they comply with relevant quality standards and identifying ways to eliminate causes of unsatisfactory results.
A. qualityplanning
B. qualityassurance
C. qualityperformance
D. quality control
5. [单选题]The receiving activities conduct analyses of the requirements with the requirements provider to ensure that a compatible, shared understanding is reached on the meaning of the requirements. The result ofthis analysis and dialog is an()set of requirements.
A. agreed-to
B. agree-to
C. agree-to-do
D. agree-with
6. [单选题]During the project, requirements change for a variety of reasons. As needs change and as work proceeds, additional requirements are derived and changes may have to be made to the existing requirements. It is essential to manage these additions and changes efficiently and effectively. To effectively analyze the impact of the changes, it is necessary that the source of each requirement is known and the rationale for any change is documented. The project manager may, however, want to track appropriate measures of requirements volatility to judge whether new or revised()are necessary.
A. proceedings
B. controls
C. forecastings
D. Prelibations
7. [单选题]Contract closeout is a process that involves()
A. Customer satisfaction analysis and final payment
B. Administrative closeout and archiving records
C. Finial contractor payment and Lessons learned
D. Product verification and administrative closeout
8. [单选题]An example of scope verification is ().
A. review the performance ofan installed software module
B. managing changes to the project schedule
C. decomposing the WBS to a work package level
D. performing a benefit/cost analysis to determine if we should proceed with the project
9. [单选题]Many of the activities performed during the preliminary investigation are still being conducted in(1),but in much greater depth than before. During this phase, the analyst must become fully aware of the (2) and must develop enough knowledge about the (3)and the existing systems to enable an effective solution to be proposed and implemented. Besides the(4)for process and data of current system, the deliverable from this phase also includes the(5)for the proposed system.
A. D
10. [单选题]Fair and(1) competition in government procurement around the world is good business and good public policy. Competitive pricing, product(2)and performanceimprovements result from competitive practices and help ensure that government authoritiesget the best (3)for the public they serve.
A. B