1. [单选题]In which form of projects origination would the project manager be likely to exercise the most control over Project resources.()

A. Strongmatrix
B. Projectized
C. Projectcoordinator
D. Weakmatrix


2. [单选题]Your project is behind schedule due to conflict between team members . Havingresolved the conflict, to get the project back on schedule , you should consider ().

A. crashing the schedule
B. performing resource leveling
C. conducting reverse resource allocation scheduling
D. utilizing the critical chain resources