必典考网发布专业英语题库2022试题多选答案+解析(09.17),更多专业英语题库的答案解析请访问必典考网高级信息系统项目管理师题库频道。
1. [单选题]Your project is behind schedule due to conflict between team members . Havingresolved the conflict, to get the project back on schedule , you should consider ().
A. crashing the schedule
B. performing resource leveling
C. conducting reverse resource allocation scheduling
D. utilizing the critical chain resources
2. [单选题]Fair and(1) competition in government procurement around the world is good business and good public policy. Competitive pricing, product(2)and performanceimprovements result from competitive practices and help ensure that government authoritiesget the best (3)for the public they serve.
A. C